Greetings @Bayo
As a builder, the cost of building a house varies from region to region. The amount you’ll finish your project depends on many factors which include the foundation type (strip, pad, raft, pile etc), the prices of materials and labour, the complexity of your house design, the type of roof, and the level of the internal finishings (basic, mid-range or luxury).
The plan for a typical semi-detached 2 bedroom bungalow ranges between NGN 50,000 - NGN 130,000 depending on the house typology and design requirement.
Our verified architects can produce a very good drawing at budget price.
N3.5m can raise the structure to first floor slab (decking) level if you:
- self-manage the project thus shaving off the extra cost of supervision or project management fee.
- are not building in a water-logged environment that requires a raft foundation
- are a bargain-hunter. Know how to get good bargain on all materials and labour without compromise.
However, NGN 4.5m will conveniently raise the structure to first floor slab level without compromise.